EssaysForStudent.com - Free Essays, Term Papers & Book Notes
Search

Impact

By:   •  Study Guide  •  254 Words  •  January 14, 2010  •  807 Views

Page 1 of 2

Join now to read essay Impact

Assumptions:-

1) Only one member of the team is required to devote his/her time for every operation apart from the person supervising apart from Phases 1 & 2 in the development stage , where two members are required

.

2)Though a member may not be directly involved in a task,he is allocated some work and is therefore paid for the entire work period.

3)There is no lag time between tasks ,and no delays occur or are accounted for

4)Three months has been considered as 90 days.

Viability of the Softwares available in the market.

Each software will require 60 days cost of purchase package (15 days for each department) which is equal to 348000

Octra

Will cost 400000 + 348000 presently . A cost of 5000 a month will be incurred after 6 months for support.

Crystal

Will

Download as (for upgraded members)  txt (1.5 Kb)   pdf (53.6 Kb)   docx (10.5 Kb)  
Continue for 1 more page »