Tucl Lms Requirements
MANAGEMENT SUMMARY
Tribhuvan University Central Library (TUCL) needs a computer-based Library Management System. It is the largest library in the Kingdom in terms of space collection and the number of members. It also serves the government ministries and foreign diplomatic missions. Therefore it functions also as a public library and to some extent as a National library .In addition to the usual Services, i.e., books circulation, Reference service and Special collections services, the TUCL also brings out Publications relevant to various subjects
The project has been scheduled to start on April 5th 2015 and is designed to be completed by the end of June 16, 2016 which budget is about NRs 2,500,000. As a project manager, I have been provided a small office with telephone, fax, computer, email and internet access and two members of support staff.
This document is divided into five sections and sub on necessary. The background section provides the purpose and scope of the project with the statement of assumption and SMART objectives. Risks that may arise during the development of the project are placed in risk section and its’ contingency plan are also identified. Costing and resources include the cost and different resources required for the project. The course of action like design, development, and implementation are included in work packages and activities in the form of work breakdown structure (WBS). Gantt chart for the development of project is also designed based on the WBS.
Contents
BACKGROUND
INTRODUCTION
Stakeholder
Scope
Statement of Assumption
SMART Objectives
Constraints
Risk
Costing and Resources
Staff
Hardware and Software
Consumables
Other Resources
Contingencies
Work Packages and Activities
EXPLANATION OF WORK BREAKDOWN STRUCTURE
Work Package 1: Project Initiation
Work Package 2: Project Planning
REQUIREMENTS
DESIGN
TESTING
DEMONSTRATION
END PROJECT
Gantt chart
Monitoring
PROGRESSION TIMELINE
Conclusion
REFERENCES
Works Cited
BACKGROUND
Tribhuvan University Central Library (TUCL) is the largest library in the Kingdom in terms of space collection and the number of members. It also serves the government ministries and foreign diplomatic Even though TUCL is an academic library established to support the teaching, study and research programmes of the university, it has extended its services beyond the limit of the university campus. In addition to the usual Services, i.e., books circulation, Reference service and Special collections services, the TUCL also brings out Publications relevant to various subjects. The library has maintained the traditional system of card catalogues for searching the materials.
INTRODUCTION
Being appointed as the Project Manager, I am responsible for organizing TUCL's computer-based Library Management System according to the scenario provided. A system has been scheduled to start on April 5, 2015 and planned to complete by June 16, 2016. The overall budget of the project is about NRs 2500,000. There is no additional cost to the project is provided but an office with telephone, fax, computer, e-mail and Internet access with two members for support staff has been provided.
Stakeholder
Stakeholder may be defined as the group of people or organization who has an interest or concern in project. The stakeholders of any organization can be its employees, customers, suppliers and investors. Similarly for these project stake holders are Staff, customer, supplier