REQUEST FOR PROPOSAL
GENERAL CONTRACTING
Cement Production Plant
Environmental Impact Study in
Frederick County, Maryland
Page
Table of Contents 2
1. PROJECT SUMMARY 3
a. Introduction 3
b. Project History 3
c. Project Objectives 3
d. Project Schedule 4
e. Maps of Project Site 5 - 6
2. SCOPE OF WORK AND EXPECTED DELIVERABLES 7
3. PROPOSAL SUBMISSION REQUIREMENTS 8
a. Letter of Intent 8
b. Statement of Experience 8
c. Company Qualifications 8
d. References 9
e. Team Qualifications 9
f. Project Understanding 9
g. Approach 9
h. Schedule 9
i. Compensation 9
4. SELECTION AND EVALUATION CRITERIA 10
5. PROPOSAL SUBMISSION AND SCHEDULE 11
a. Process Schedule 11
b. RFP Contact 11
6. PRE-PROPOSAL ACTIVITIES 12
a. Pre-Bid Meeting 12
b. Questions and Clarifications 12
7. SUPPLIER LIST* 13
* Supplier List found using Google.com and searching under “Environmental Consultants”.
1. PROJECT SUMMARY
a. Introduction
General Contracting is planning on building a cement production plant in the town of Middletown, in Frederick County, Maryland. As part of the process an environmental impact study must be undertaken before the county can issue a permit to begin construction.