Implementation Plan and Control System: Backyard Remodelling

Page 1 of 9

IMPLEMENTATION PLAN AND CONTROL SYSTEM: BACKYARD REMODELLING

Presented to Dr. S. Lakhal

As part of the course requirements for

OPER 4016 EL-12: Project Management

Presented by Group M:

Devaughan Forrest

Laurentian University

Sunday, June 24th, 2018

Table of Contents

  1.  VERSION CONTROL- …………………………………………………………….3
  2.   PROJECT SUMMARY……………………………………………………………..3
  3.   LEGAL WARNING ………………………………………………………………...4

     4.      PROJECT SCOPE/ PURPOSE/OBJECTIVES …………………….……………4

     5.     INTRODUCTION OF THE TEAM’S ROLES AND RESPONSIBILITIES...…4

      6.    CONTACT PERSON/CONTACT DETAILS ………………………………………5

      7.    COMMUNICATION PLAN….……………………………………………….……5

      8.    BASELINE SCHEDULE……………………………………………………………6

       9.    PROJECT RISK ASSESSMENT ………………………………………………...6

      10.   BUDGET CONTROL……………………………………………………………..7

      11.   QUALITY ASSURANCE AND QUALITY CONTROL……………….…….…7

     12.   PROCUREMENT CONTROL ………………………………………….….…….7

     13.   DESIGN CONTROL ……………………………………………………….....…...7

     14.   CHANGE MANAGEMENT PROCESS …………………………………...……8

     15.    DOCUMENT CONTROL …………………………………………..……….…..9

     16.    NETWORK DIAGRAM/PATHS. ……………………………..…………….…9

17.APPENDICES

Appendix A - Responsibility Assignment Matrix (RAM) …………….. 10

Appendix B - Communications Plan …………………………………... 11

Appendix C - Gantt Chart…………………………………………...……12

Appendix D - Project Budget Template…………………………………..13

Appendix E - Change Request Form…………………………………..…14

Appendix F - Change Impact Analysis………………………………..….15

Appendix G - Network Diagram…………………………………..………16

1. Version Control

This document is version 1 of the implementation plan and control systems for the backyard remodelling project at 1234 Project St. in Sudbury, ON. This version is subject to change as the project develops and will be identified as version 2 and so forth.

2. Project Summary

TCCUM Contracting Inc. plans to create an extraordinary outdoor paradise in Mr. and Mrs. Smith’s backyard. How the company intends to execute this plan is outlined in this document. The goal of this project is to remodel the backyard of Mr. and Mrs. Smith’s residence located at 1234 Project St. in Sudbury, ON. The lot has dimensions of approximately 4,300 square feet. The following components will be implemented in the remodelling design:

  1. A garden oasis which includes a variety of plants and vegetation.
  2. A relaxing hot tub and sauna area overlooking the garden.
  3. A fully equipped patio (complete with kitchen & barbeque area) that can entertain   family and friends.

Project Version

Project Name

Property Address

Project Sponsor/Customer

Version #1

Remodeling Backyard

1234 Project St.

Sudbury, ON

Mr&MrsSmith,  property owners

Project Manager (PM)

Project Steering Committee

Project

Participants: Design team

Consultants

Contractors & Subcontractors

  1. Don, Kyle, PEng.
  1. Bissessur, Chaya (Gardener)
  2. Francis, Chelsea (Plumber)
  3. Jeyaseelan,  Umah (Electrician)
  4. Sem, May (Carpenter)
  5. Audet, Tanya (Architect)
  1. Audet, Tanya (Architect)
  2. Francis, Chelsea (Plumber)

  1. Don, Kyle, PEng. (Project Manager)
  1. Jeyaseelan,  Umah (Electrician)

To be selected by Steering Committee

Project Type

Platform

Number of Phase

Construction

SharePoint

Two phases

Project Start Date

Project End Date

Total Estimated Cost

June 17, 2018

August 13, 2018

$125,000